Project: 4924 Hebei Chongli Jiaocheshan 49.3MW Wind Farm Project - Request for post-registration changes
Project 4924 Hebei Chongli Jiaocheshan 49.3MW Wind Farm Project
PRC ref PRC-4924-001
Process track Prior approval
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 01 Dec 11 - 30 Nov 18
Assessment opinion Assessment opinion (195 KB)
Revised PDD Revised PDD (666 KB)   Revised PDD - track changes (685 KB)
Supplementary documents
Signed form Signed form (50 KB)
DOE clarification DOE clarification 1 - Response for Clarification_ Jiaocheshan_Ref.4924.pdf (48 KB)
VVS version VVS 2.0
Current status 18 Dec 12 - Approved
Effective approval date: 18 Dec 12
Historic statuses 06 Nov 12 - Published
15 Nov 12 - Awaiting DOE clarifications
17 Nov 12 - DOE clarifications received
17 Nov 12 - Summary note being prepared
27 Nov 12 - Awaiting EB decision