Project: 2716 Grid connected energy efficient power generation - Request for post-registration changes
Project 2716 Grid connected energy efficient power generation
PRC ref PRC-2716-001
Process track Prior approval
DOE SGS
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? No

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No
Applicable crediting period 01 Feb 11 - 31 Jan 21
Assessment opinion Assessment opinion (263 KB)
Revised PDD Revised PDD (946 KB)   Revised PDD - track changes (991 KB)
Supplementary documents
Signed form Signed form (1921 KB)
DOE clarification DOE clarification 1 - Assessment Opinion.pdf (341 KB)
DOE clarification 2 - PDD v6.1_C.pdf (946 KB)
DOE clarification 3 - PDD v6.1_TC.pdf (991 KB)


VVS version VVS 2.0
Current status 18 Feb 13 - Approved
Effective approval date: 13 Feb 13
Historic statuses 26 Nov 12 - Published
02 Jan 13 - Awaiting DOE clarifications
15 Jan 13 - DOE clarifications received
15 Jan 13 - Summary note being prepared
23 Jan 13 - Awaiting EB decision