Project: 7606 Reduction of N2O emissions from the new nitric acid plant of Egypt Hydrocarbon Corporation at Ain Sokhna - Request for post-registration changes
Project 7606 Reduction of N2O emissions from the new nitric acid plant of Egypt Hydrocarbon Corporation at Ain Sokhna
PRC ref PRC-7606-001
Process track Prior approval
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Change a version of methodology
Methodology(ies) list ACM0019 ver. 4 - N2O abatement from nitric acid production
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Changes to the project or programme design
  • Changes have an impact on: Actual operational parameters differ from the expected parameters, Voluntary update of the applied methodologies to a later valid version or voluntary change to other methodologies

Change to the start date of the crediting period
  • Proposed start date of crediting period: 01 Jan 2024
Applicable crediting period 01 Jul 14 - 30 Jun 21
Assessment opinion Assessment opinion (756 KB)
Revised PDD Revised PDD (672 KB)   Revised PDD - track changes (875 KB)
Supplementary documents Appendix 1 - Dummy.txt (53 bytes)
Appendix 2 - Dummy.txt (53 bytes)
Signed form Signed form (248 KB)
DOE clarification DOE clarification 1 - 2022-05-19_PRC Report_2-0 final.pdf (680 KB)





DOE clarification 7 - 7606_PRC_PDD v.02.2.pdf (672 KB)
DOE clarification 8 - 7606_PRC_PDD v.02.2_TRACK.pdf (673 KB)
DOE clarification 9 - 2022-06-14_PRC Report_3-0 final.pdf (683 KB)
VVS version VVS-PA 3.0
Current status 14 Sep 22 - Rejected
Effective rejection date: 08 Sep 22. Reason (71 KB)
Historic statuses 21 Apr 22 - Published
31 May 22 - Awaiting DOE clarifications
14 Jun 22 - DOE clarifications received
14 Jun 22 - Summary note being prepared
29 Jul 22 - Request added to EB115 meeting agenda