Project: 5312 UPC Linghai Xibaqian 49.5 MW Wind Farm Liaoning - Request for post-registration changes
Project 5312 UPC Linghai Xibaqian 49.5 MW Wind Farm Liaoning
PRC ref PRC-5312-001
Process track Issuance
DOE TÜV NORD
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 19 Oct 11 - 18 Oct 18
Assessment opinion Assessment opinion (337 KB)
Revised PDD Revised PDD (1366 KB)   Revised PDD - track changes (1339 KB)
Supplementary documents
Signed form Signed form (50 KB)
DOE clarification
VVS version VVS 2.0
Current status 17 Apr 13 - Approved
Effective approval date: 17 Apr 13
Historic statuses 19 Mar 13 - Request published