Project: 4516 MNI Renewable Energy Plant - Request for post-registration changes
Project 4516 MNI Renewable Energy Plant
PRC ref PRC-4516-001
Process track Issuance
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Oct 2011 - 30 Apr 2012

Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Oct 11 - 30 Sep 21
Assessment opinion Assessment opinion (291 KB)
Revised PDD Revised PDD (1100 KB)   Revised PDD - track changes (1634 KB)
Supplementary documents
Signed form Signed form (163 KB)
DOE clarification
VVS version VVS 2.0
Current status 08 Apr 13 - Approved
Effective approval date: 08 Apr 13
Historic statuses 08 Mar 13 - Request published