Project: 8785 75MW Yunnan Nuozu Hydropower Project - Request for post-registration changes
Project 8785 75MW Yunnan Nuozu Hydropower Project
PRC ref PRC-8785-002
Process track Issuance
DOE CCCI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes
Applicable crediting period 01 Jan 13 - 31 Dec 19
Assessment opinion Assessment opinion (294 KB)
Revised PDD Revised PDD (1216 KB)   Revised PDD - track changes (1282 KB)
Supplementary documents Appendix 1 - List of documents submitted_NuozuPRC.pdf (35 KB)
Signed form Signed form (52 KB)
DOE clarification
VVS version VVS 2.0
Current status 19 May 17 - Approved
Effective approval date: 19 May 17
Historic statuses 20 Apr 17 - Request published