Project: 0941 Sudokwon Landfill Gas Electricity Generation Project (50MW) - Request for post-registration changes
Project 0941 Sudokwon Landfill Gas Electricity Generation Project (50MW)
PRC ref PRC-0941-003
Process track Prior approval
DOE KFQ
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: Addition of new components or extension/addition of technologies/measures that introduce:
Applicable crediting period 30 Apr 07 - 29 Apr 17
Assessment opinion Assessment opinion (437 KB)
Revised PDD Revised PDD (2055 KB)   Revised PDD - track changes (2076 KB)
Supplementary documents
Signed form Signed form (983 KB)
DOE clarification DOE clarification 1 - Response to clarification_Project no.0941_KFQ_16012017_final.pdf (92 KB)
VVS version VVS 2.0
Current status 07 Feb 17 - Approved
Effective approval date: 07 Feb 17
Historic statuses 30 Dec 16 - Published
04 Jan 17 - Awaiting DOE clarifications
17 Jan 17 - DOE clarifications received
17 Jan 17 - Summary note being prepared
17 Jan 17 - Awaiting EB decision