Project:
9392 5 MW Solar PV Power Project at NTPC-Dadri, a Business unit of NTPC limited
- Request for post-registration changes
Project | 9392 5 MW Solar PV Power Project at NTPC-Dadri, a Business unit of NTPC limited |
---|---|
PRC ref | PRC-9392-001 |
Process track | Issuance |
DOE | URS |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Corrections that do not affect project design
|
Applicable crediting period | 01 Jan 13 - 31 Dec 19 |
Assessment opinion |
![]() |
Revised PDD |
![]() ![]() |
Supplementary documents | |
Signed form |
![]() |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 27 Jun 16 -
Approved
Effective approval date: 27 Jun 16
|
Historic statuses |
27 May 16 -
Request published |