Project: 6762 Methane Capture and Utilization Project at Carotino Palm Oil Mill, Malaysia - Request for post-registration changes
Project 6762 Methane Capture and Utilization Project at Carotino Palm Oil Mill, Malaysia
PRC ref PRC-6762-001
Process track Prior approval
DOE Carbon Check
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? No

Change to the start date of the crediting period
  • Proposed start date of crediting period: 20 Dec 2014
Applicable crediting period 20 Dec 14 - 19 Dec 24
Assessment opinion Assessment opinion (715 KB)
Revised PDD Revised PDD (950 KB)   Revised PDD - track changes (1193 KB)
Supplementary documents Appendix 1 - PRC_ex-ante ER_Carotino POME_WWT.xlsx (347 KB)
Signed form Signed form (6896 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 21 Sep 20 - Approved
Effective approval date: 20 Sep 20
Historic statuses 17 Aug 20 - Published
17 Aug 20 - Summary note being prepared
31 Aug 20 - Awaiting EB decision