Project: 3897 Electric Power Generation from Renewable Sources – Barra da Paciência, Ninho da Águia, Corrente Grande, Paiol, São Gonçalo and Várzea Alegre Small Hydropower Plants - Request for post-registration changes
Project 3897 Electric Power Generation from Renewable Sources – Barra da Paciência, Ninho da Águia, Corrente Grande, Paiol, São Gonçalo and Várzea Alegre Small Hydropower Plants
PRC ref PRC-3897-001
Process track Prior approval
DOE Earthood
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes Prior to commencement of a verification for the project activity or PoA stated above
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on:
Applicable crediting period 16 Jan 13 - 15 Jan 20
Assessment opinion Assessment opinion (2686 KB)
Revised PDD Revised PDD (2693 KB)   Revised PDD - track changes (2925 KB)
Supplementary documents
Signed form Signed form (116 KB)
DOE clarification DOE clarification 1 - CDM.VAL.19.156_Response for request for clarification_Barra da Paciencia_revised.pdf (154 KB)
DOE clarification 2 - 20200929_Barra da Paciencia_Revised PDD_PRC_CLEAN.pdf (3037 KB)
DOE clarification 3 - 20200929_Barra da Paciencia_Revised PDD_PRC_track changes.pdf (2925 KB)
DOE clarification 4 - CDM.VAL.19.156_FValRep PRC_Barra Paciencia_revised_with annexes CLEAN.pdf (2768 KB)
DOE clarification 5 - CDM.VAL.19.156_Reg_form PRC_Barra Paciencia.pdf (125 KB)
VVS version VVS-PA 2.0
Current status 09 Nov 20 - Approved
Effective approval date: 08 Nov 20
Historic statuses 07 Sep 20 - Published
21 Sep 20 - Awaiting DOE clarifications
05 Oct 20 - DOE clarifications received
05 Oct 20 - Summary note being prepared
19 Oct 20 - Awaiting EB decision