Project: 7093 Los Cocos Wind Farm Project - Request for post-registration changes
Project 7093 Los Cocos Wind Farm Project
PRC ref PRC-7093-001
Process track Issuance
DOE ICONTEC
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Temporary deviations from the monitoring plan or the monitoring methodology
  • Applicable period for proposed deviations (inclusive): 01 Mar 2013 - 31 Dec 2017
Assessment opinion Assessment opinion (778 KB)
Revised PDD  
Supplementary documents
Signed form Signed form (229 KB)
DOE clarification
VVS version VVS-PA 2.0
Current status 04 Oct 19 - Approved
Effective approval date: 04 Oct 19
Historic statuses 05 Sep 19 - Request published