17:30 26 Oct 25
Project:
3854 20 MW Enercon Wind farms (SAI) Pvt. Limited in Maharashtra
- Request for post-registration changes
| Project | 3854 20 MW Enercon Wind farms (SAI) Pvt. Limited in Maharashtra |
|---|---|
| PRC ref | PRC-3854-002 |
| Process track | Prior approval |
| DOE | Earthood |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 14 Dec 10 - 13 Dec 20 |
| Assessment opinion |
Assessment opinion (330 KB)
|
| Revised PDD |
Revised PDD (5373 KB)
Revised PDD - track changes (4476 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (165 KB)
|
| DOE clarification |
|
| VVS version | VVS-PA 1.0 |
| Current status | 06 Oct 17 -
Approved
Effective approval date: 05 Oct 17
|
| Historic statuses |
22 Aug 17 -
Published 05 Sep 17 - Awaiting DOE clarifications 14 Sep 17 - DOE clarifications received 14 Sep 17 - Summary note being prepared 15 Sep 17 - Awaiting EB decision |