Project: 8099 Lautaro Generation Project - Request for post-registration changes
Project 8099 Lautaro Generation Project
PRC ref PRC-8099-002
Process track Issuance
DOE LGAI Tech. Center S.A
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on: Actual operational parameters differ from the expected parameters
Applicable crediting period 31 Jan 13 - 30 Jan 20
Assessment opinion Assessment opinion (240 KB)
Revised PDD Revised PDD (2029 KB)   Revised PDD - track changes (2280 KB)
Supplementary documents Appendix 1 - 8099 Investment Analysis vPRC.xls (341 KB)
Appendix 2 - 8099 CER Calculation_PRC_v4.xls (179 KB)
Appendix 3 - PE comparison ex-ante vs PRC_v01.xlsx (59 KB)
Signed form Signed form (79 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 26 Jan 24 - Approved
Effective approval date: 26 Jan 24
Historic statuses 28 Dec 23 - Request published