14:16 09 Jan 25
Project:
4131 Xiyinghe Sangou Bundled Hydropower Project
- Request for post-registration changes
Project | 4131 Xiyinghe Sangou Bundled Hydropower Project |
---|---|
PRC ref | PRC-4131-001 |
Process track | Prior approval |
DOE | CQC |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | Prior to commencement of a verification for the project activity or PoA stated above |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
|
Assessment opinion | Assessment opinion (208 KB) |
Revised PDD | |
Supplementary documents |
Appendix 1 - 向 (113 KB)
Appendix 2 - Emission Reduction Calculation Sangou Bundled-deviation.xls (76 KB) |
Signed form | Signed form (187 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 26 Sep 12 -
Approved
Effective approval date: 25 Sep 12
|
Historic statuses |
21 Aug 12 -
Published 21 Aug 12 - Summary note being prepared 04 Sep 12 - Awaiting EB decision |