14:27 12 Dec 24
Project:
6447 Zhejiang Tangcun 32MW Hydropower Project
- Request for post-registration changes
Project | 6447 Zhejiang Tangcun 32MW Hydropower Project |
---|---|
PRC ref | PRC-6447-001 |
Process track | Issuance |
DOE | RINA |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
|
Assessment opinion | Assessment opinion (653 KB) |
Revised PDD | |
Supplementary documents | |
Signed form | Signed form (84 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 01 Aug 13 -
Approved
Effective approval date: 01 Aug 13
|
Historic statuses |
03 Jul 13 -
Request published |