Project: 5740 3 MW Hydro Power Project by Oreva Energy Pvt. Ltd - Request for post-registration changes
Project 5740 3 MW Hydro Power Project by Oreva Energy Pvt. Ltd
PRC ref PRC-5740-001
Process track Issuance
DOE Earthood
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard? Yes

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Feb 12 - 31 Jan 22
Assessment opinion Assessment opinion (213 KB)
Revised PDD Revised PDD (868 KB)   Revised PDD - track changes (917 KB)
Supplementary documents Appendix 1 - UN5740 IRR_Oreva_3_MW_ PRC.xls (232 KB)
Signed form Signed form (42 KB)
DOE clarification
VVS version VVS 9.0
Current status 07 Oct 16 - Approved
Effective approval date: 07 Oct 16
Historic statuses 08 Sep 16 - Request published