04:15 10 Jan 25
Project:
3296 14MW MIRAE ASSET PV(photovoltaic) power plant bundling project
- Request for post-registration changes
Project | 3296 14MW MIRAE ASSET PV(photovoltaic) power plant bundling project |
---|---|
PRC ref | PRC-3296-001 |
Process track | Issuance |
DOE | KSA |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
Applicable crediting period | 16 Oct 10 - 15 Oct 17 |
Assessment opinion | Assessment opinion (255 KB) |
Revised PDD | Revised PDD (4539 KB) Revised PDD - track changes (4564 KB) |
Supplementary documents |
Appendix 1 - Economic analysis_MIRAE(120809).xlsx (375 KB)
|
Signed form | Signed form (130 KB) |
DOE clarification | |
VVS version | VVS 2.0 |
Current status | 30 Nov 12 -
Approved
Effective approval date: 30 Nov 12
|
Historic statuses |
01 Nov 12 -
Request published |