Project: 3296 14MW MIRAE ASSET PV(photovoltaic) power plant bundling project - Request for post-registration changes
Project 3296 14MW MIRAE ASSET PV(photovoltaic) power plant bundling project
PRC ref PRC-3296-001
Process track Issuance
DOE KSA
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard? Yes

Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 16 Oct 10 - 15 Oct 17
Assessment opinion Assessment opinion (255 KB)
Revised PDD Revised PDD (4539 KB)   Revised PDD - track changes (4564 KB)
Supplementary documents Appendix 1 - Economic analysis_MIRAE(120809).xlsx (375 KB)
Signed form Signed form (130 KB)
DOE clarification
VVS version VVS 2.0
Current status 30 Nov 12 - Approved
Effective approval date: 30 Nov 12
Historic statuses 01 Nov 12 - Request published