Project:
6787 Wang Phloeng Solar Power Plant Project
- Request for post-registration changes
| Project | 6787 Wang Phloeng Solar Power Plant Project |
|---|---|
| PRC ref | PRC-6787-001 |
| Process track | Issuance |
| DOE | GLC |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 02 May 13 - 01 May 20 |
| Assessment opinion |
Assessment opinion (222 KB)
|
| Revised PDD |
Revised PDD (1678 KB)
Revised PDD - track changes (1703 KB)
|
| Supplementary documents |
Appendix 1 - Wang Phloeng solar ER calculation (PDD) 20140228.xlsx (17 KB)
|
| Signed form |
Signed form (2165 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 10 Jul 14 -
Approved
Effective approval date: 10 Jul 14
|
| Historic statuses |
11 Jun 14 -
Request published |

Assessment opinion