23:23 08 Nov 24
Project:
8288 IOT Mabagas Limited power plant, Pudhuchatram
- Request for post-registration changes
Project | 8288 IOT Mabagas Limited power plant, Pudhuchatram |
---|---|
PRC ref | PRC-8288-001 |
Process track | Issuance |
DOE | Earthood |
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
Methodology(ies) list | |
Standardized baseline(s) list | |
DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
Applicable crediting period | 01 Jan 13 - 31 Dec 22 |
Assessment opinion | Assessment opinion (297 KB) |
Revised PDD | Revised PDD (1568 KB) Revised PDD - track changes (1577 KB) |
Supplementary documents |
Appendix 1 - 8288 ER Sheet_200313.xlsx (12 MB)
Appendix 2 - 8288 Verification report_clean.pdf (885 KB) |
Signed form | Signed form (125 KB) |
DOE clarification | |
VVS version | VVS-PA 2.0 |
Current status | 22 May 20 -
Approved
Effective approval date: 22 May 20
|
Historic statuses |
23 Apr 20 -
Request published |
Offset now: visit the United Nations Carbon Offset Platform