23:12 07 Nov 25
Project:
8288 IOT Mabagas Limited power plant, Pudhuchatram
- Request for post-registration changes
| Project | 8288 IOT Mabagas Limited power plant, Pudhuchatram |
|---|---|
| PRC ref | PRC-8288-001 |
| Process track | Issuance |
| DOE | Earthood |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
No changes |
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Temporary deviations from the monitoring plan or the monitoring methodology
Corrections that do not affect project design
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 01 Jan 13 - 31 Dec 22 |
| Assessment opinion |
Assessment opinion (297 KB)
|
| Revised PDD |
Revised PDD (1568 KB)
Revised PDD - track changes (1577 KB)
|
| Supplementary documents |
Appendix 1 - 8288 ER Sheet_200313.xlsx (12 MB)
Appendix 2 - 8288 Verification report_clean.pdf (885 KB)
|
| Signed form |
Signed form (125 KB)
|
| DOE clarification | |
| VVS version | VVS-PA 2.0 |
| Current status | 22 May 20 -
Approved
Effective approval date: 22 May 20
|
| Historic statuses |
23 Apr 20 -
Request published |

Assessment opinion
Appendix 1 - 8288 ER Sheet_200313.xlsx
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: