Project: 7313 Bundled Yeonggwang(II)-Yecheon PV (Photovoltaic) Power Plant Project in KHNP - Request for post-registration changes
Project 7313 Bundled Yeonggwang(II)-Yecheon PV (Photovoltaic) Power Plant Project in KHNP
PRC ref PRC-7313-001
Process track Issuance
DOE KFQ
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 01 Jan 13 - 31 Dec 22
Assessment opinion Assessment opinion (231 KB)
Revised PDD Revised PDD (1192 KB)   Revised PDD - track changes (1374 KB)
Supplementary documents Appendix 1 - Emission Reduction_version02.xlsx (264 KB)
Signed form Signed form (126 KB)
DOE clarification
VVS version VVS 2.0
Current status 06 Feb 15 - Approved
Effective approval date: 06 Feb 15
Historic statuses 08 Jan 15 - Request published