Project: 0396 Satyamaharshi 6 MW Biomass Power Project - Request for post-registration changes
Project 0396 Satyamaharshi 6 MW Biomass Power Project
PRC ref PRC-0396-001
Process track Issuance
DOE DNV
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Changes to the project or programme design
  • Changes have an impact on: None of the above
Applicable crediting period 23 Jul 04 - 22 Jul 11
Assessment opinion Assessment opinion (68 KB)
Revised PDD Revised PDD (397 KB)   Revised PDD - track changes (412 KB)
Supplementary documents
Signed form Signed form (163 KB)
DOE clarification
VVS version VVS 2.0
Current status 24 Jan 13 - Approved
Effective approval date: 24 Jan 13
Historic statuses 26 Dec 12 - Request published