4981 CECIC Shizuishan Grid-connected Solar PV Power Generation Phase I project
- Request for post-registration changes
| Project | 4981 CECIC Shizuishan Grid-connected Solar PV Power Generation Phase I project |
|---|---|
| PRC ref | PRC-4981-001 |
| Process track | Issuance |
| DOE | BVI |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
|
| Applicable crediting period | 11 Jul 11 - 10 Jul 18 |
| Assessment opinion |
Assessment opinion (289 KB)
|
| Revised PDD |
Revised PDD (853 KB)
Revised PDD - track changes (801 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (317 KB)
|
| DOE clarification | |
| VVS version | VVS 2.0 |
| Current status | 07 Jan 13 -
Approved
Effective approval date: 07 Jan 13
|
| Historic statuses |
08 Dec 12 -
Request published |