Project: 7939 Binwa-IV Hydro Electric Project - Request for post-registration changes
Project 7939 Binwa-IV Hydro Electric Project
PRC ref PRC-7939-001
Process track Issuance
DOE BVI
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes
No changes
Methodology(ies) list
Standardized baseline(s) list
DOE conducted validation of the changes When performing a verification for the project activity or PoA stated above (See footnote 1 below)
Type of submission Corrections that do not affect project design
  • All changes are in Appendix 1 of the CDM project standard?

Permanent changes from the monitoring plan or the monitoring methodology
  • All changes are in Appendix 1 of the CDM project standard?

Changes to the project or programme design
  • Changes have an impact on: Decrease in the capacity
Applicable crediting period 01 Dec 13 - 30 Nov 20
Assessment opinion Assessment opinion (195 KB)
Revised PDD Revised PDD (1466 KB)   Revised PDD - track changes (1697 KB)
Supplementary documents
Signed form Signed form (472 KB)
DOE clarification
VVS version VVS-PA 3.0
Current status 11 Nov 22 - Approved
Effective approval date: 11 Nov 22
Historic statuses 13 Oct 22 - Request published