- Request for review

A review has been requested by either a Party involved or at least three Board members for the below listed requests for issuance.

The review will be processed in accordance with the CDM project cycle procedure

The following table lists the requests for issuance of CDM project actvities for which review has been requested. A schedule for the reviews of these requests can be found here.

Total: 2 request(s) of 42,146 CERs.
Ref Title Monitoring period Amount of CERs
Request for review
Reasons for review EB meeting
3378 Landfill Gas Recovery and Flaring Project in the El Verde Landfill, León.
27 Oct 2017 - 31 Dec 2018 42146 Request 1
Request 2
Request 3
Request 4
Request 5
Request 6
-
7726 Kainji Hydropower Rehabilitation Project, Nigeria
01 Jan 2013 - 31 Dec 2017 0 Request 1
Request 2
Request 3
-


The following table lists the requests for issuance of CDM programme of activities for which review has been requested.

Ref Title Monitoring period Amount of CERs
Request for review
Reasons for review EB meeting 1)
7359 PoA for the Reduction of emission from non-renewable fuel from cooking at household level 28 May 2014 –02 May 2017 1547968