12:19 21 Apr 25
Project:
9416-P1-0006-CP1 Bhud Wind power project, Maharashtra
- Request for post-registration changes
Project | 9416-P1-0006-CP1 Bhud Wind power project, Maharashtra |
---|---|
PRC ref | PRC-9416-004 |
Process track | CPA-PRC |
DOE | KBS |
Type of submission |
Changes to the project or programme design
|
Applicable crediting period | 29 Dec 14 - 28 Dec 21 |
Assessment opinion |
![]() |
Revised CPA-DD |
![]() ![]() |
Supplementary documents |
![]() ![]() |
Signed form |
![]() |
DOE clarification |
![]() |
VVS version | VVS-PoA 3.0 |
Current status | 01 Dec 22 -
Approved
Effective approval date: 30 Nov 22
|
Historic statuses |
04 Oct 22 -
Published 18 Oct 22 - Awaiting DOE clarifications 28 Oct 22 - DOE clarifications received 28 Oct 22 - Summary note being prepared 10 Nov 22 - Awaiting EB decision |
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: