Project: 6198-P1-0004-CP1 Zaña Hydro Power Plant, Monte Seco1 – Tunki PoA CPA #3 - Request for post-registration changes
Project 6198-P1-0004-CP1 Zaña Hydro Power Plant, Monte Seco1 – Tunki PoA CPA #3
PRC ref PRC-6198-003
Process track CPA-PRC
DOE Carbon Check
Type of submission Corrections that do not affect project design

Changes to the project or programme design
  • Is the change to increase the capacity specified in the included CPA-DD? Yes Date of the commissioning or implementation of the change: 29 Dec 2018 Is the change to decrease the capacity specified in the included CPA-DD? No Is the change to add new components or extend/add technologies/measures or introduce complementary technologies/measures? No Date of the commissioning or implementation of the change:
Applicable crediting period 01 Oct 16 - 30 Sep 23
Assessment opinion Assessment opinion (738 KB)
Revised CPA-DD Revised CPA-DD (1084 KB)   Revised CPA-DD - track changes (1063 KB)
Supplementary documents Appendix 1 - EFgrid-DD Zaña-rev-v2.xlsm (11 MB)
Appendix 2 - CF_Zaña-updated.xls (243 KB)
Signed form Signed form (2246 KB)
DOE clarification
VVS version VVS-PoA 2.0
Current status 15 Sep 20 - Approved
Effective approval date: 14 Sep 20
Historic statuses 10 Aug 20 - Published
10 Aug 20 - Summary note being prepared
25 Aug 20 - Awaiting EB decision