ACM0015: Consolidated baseline and monitoring methodology for project activities using alternative raw materials that do not contain carbonates for clinker manufacturing in cement kilns --- Version 2.0 --- ON HOLD

Submit comments for improvement of this methodology (please login)

Title Consolidated baseline and monitoring methodology for project activities using alternative raw materials that do not contain carbonates for clinker manufacturing in cement kilns (457 KB)

The additionality of the project activity shall be demonstrated and assessed using the Tool for the demonstration and assessment of additionality (318 KB)

Other tool referenced in this methodology:

Version number
2.0
Scale Large scale --- Consolidated
Status Not Active (old version) On Hold

The Board agreed to suspend the use of the methodologies ACM0013 version 02.1 and ACM0015 version 02 by putting them on hold, with immediate effect hence, the revised methodologies ACM0013 version 03 and ACM0015 version 03 shall be deemed effective 26 March 2010 (2400 hours GMT).

Validity Valid from 08 Apr 09 to 25 Mar 10
(See Procedures (210 KB), section IV)
Sectoral scope(s) 4
Sources Replaces: AM0033 , AM0040
Revisions* Clarification with regards to the applicability of the methodology to greenfield plants and modification of the equations (4) and (13) to have consistent units of parameters (submitted 31 Dec 09): AM_REV_0179 (184 KB)
Previous Versions
Title Consolidated baseline and monitoring methodology for project activities using alternative raw materials that do not contain carbonates for clinker manufacturing in cement kilns --- Version 1 (412 KB)
Version number 1.0
Validity Valid from 30 Nov 07 to 07 Apr 09
Requests for registration can be submitted until 07 Dec 2009 23:59:59 GMT
Sectoral scope(s) 4
Clarifications* Meth applicability to greenfield projects (submitted 09 May 08): AM_CLA_0084 (28 KB)
Revisions* Revision is proposed to modify the applicability conditions of the availability of alternative material for clinker manufacturing in order to improve the use of the amount of AMC that in project activity conditions shall be stored or not be used in any case. (submitted 08 Dec 08): AM_REV_0133 (148 KB)

* Only the requests for clarification and revision that have been clarified by the Meth Panel are displayed. To view all requests for clarification, go to this page. To view all requests for revision, go to this page.