18:36 08 Apr 25
ACM0001:
Consolidated methodology for landfill gas project activities --- Version 2.0
Submit comments for improvement of this methodology (please login)
Title |
![]()
The additionality of the project activity shall
be demonstrated and assessed using the
|
|
---|---|---|
Version number |
|
|
Scale | Large scale --- Consolidated | |
Status | Not Active (old version) | |
Validity |
Valid from 29 Sep 05 to 17 May 06
|
|
Sectoral scope(s) | 13 | |
Sources |
AM0002
,
AM0003
,
AM0010
,
AM0011
Replaces: AM0002 , AM0003 , AM0010 , AM0011 |
|
Clarifications* |
Parameters to be fixed ex-ante for the entire crediting period
(submitted 23 Dec 05):
![]() |
|
Clarification on requirements for monitoring landfill gas flows
(submitted 23 Feb 06):
![]() |
||
Requirement for separate monitoring of LFG temperature and pressure
(submitted 08 Mar 06):
![]() |
||
Clarification on requirements for monitoring landfill gas flows in projects where only flaring occurs
(submitted 27 Apr 06):
![]() |
||
Revisions* |
Alternative approaches to monitoring flare efficiency
(submitted 26 Apr 06):
![]() |
|
Previous Versions | ||
Title |
![]() |
|
Version number | 1.0 | |
Validity | Valid from 02 Sep 04 to 11 Oct 05 | |
Sectoral scope(s) | 13 | |
Clarifications* |
Request for clarification on step 0 of the “Tool for the demonstration and assessment of additionality"
(submitted 04 Oct 05):
![]() |
|
Request for clarification on the applicability of the Methodology ACM0001 to project types that supply compressed LFG by trucks to end-users
(submitted 14 Dec 12):
![]() |
||
Procedure to determine the amount of methane that would have been captured and destroyed (by flaring) in the baseline (FCH4,BL,y)
(submitted 04 Feb 15):
![]() |
* Only the requests for clarification and revision that have been clarified by the Meth Panel are displayed. To view all requests for clarification, go to this page. To view all requests for revision, go to this page.