AMS-I.D.: Grid connected renewable electricity generation --- Version 15.0

Submit comments for improvement of this methodology (please login)

Title Grid connected renewable electricity generation (267 KB)

Tool referenced in this methodology:

Version number
15.0
Scale Small scale
Status Not Active (old version)
Validity Valid from 30 Oct 09 to 10 Jun 10
Sectoral scope(s) 1
Clarifications/Revisions* Degummed and neutralized oil as biomass (submitted 18 Nov 09): SSC_368 (242 KB)
Clarification on the monitoring of net electricity in AMS-I.D (submitted 07 Dec 09): SSC_371 (205 KB)
Revision of AMS-I.D to include an additional option for EGestimated,y determination (submitted 05 Jan 10): SSC_378 (255 KB)
Clarification on the distinction between a new and existing reservoir (submitted 19 Mar 10): SSC_398 (196 KB)
Clarification on the thresholds' criteria for qualifying limits for bundled SSC CDM project activities (submitted 10 Mar 10): SSC_400 (205 KB)
Monitoring of electricity supplied to grid connected users in AMS-I.D (submitted 26 Mar 10): SSC_409 (230 KB)
Applicability of AMS-I.D to grid connected biomass integrated gasification combined cycle (BIGCC) plant (submitted 11 May 10): SSC_419 (480 KB)
Previous Versions
Title Grid connected renewable electricity generation (79 KB)
Version number 14.0
Validity Valid from 31 Jul 09 to 29 Oct 09
Requests for registration can be submitted until 29 Jun 2010 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Clarification on the 15 MW eligibility limit for small-scale renewable energy projects (submitted 02 Aug 09): SSC_338 (152 KB)
Clarification regarding the consideration of biomass assessment and leakage under AMS-I.D (submitted 18 Nov 09): SSC_366 (326 KB)
Revision of AMS-I.D for renewable energy units delivering power to newly developed grids in the context of a PoA (submitted 21 Dec 09): SSC_377 (240 KB)
Revision to AMS-I.D to include cover crops of short-cycle cellulosic biomass from non-dedicated plantations (submitted 17 Jan 10): SSC_380 (270 KB)
Title Grid connected renewable electricity generation (298 KB)
Version number 13.0
Validity Valid from 14 Dec 07 to 30 Jul 09
Requests for registration can be submitted until 30 Mar 2010 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Clarification on AMS I.D. v12 on the installation of a backpressure turbine generator to a steam source that is in the baseline set-up (submitted 07 Jan 08): SSC_154 (139 KB)
Fossil fuel combustion in hydro projects (submitted 28 Jan 08): SSC_159 (138 KB)
Power output to grid in hydro projects (submitted 27 Feb 08): SSC_164 (165 KB)
Clarification on use of AMS-I.C and AMS-I.D for a project using biogas from gas water (submitted 19 Feb 08): SSC_173 (173 KB)
Clarification Request on Applicability of AMS. I.D. to a Project Activity, Which Will Sell Electricity to a Plant Instead of to a Provincial Grid. (submitted 28 Jul 08): SSC_204 (138 KB)
Applicability of AMS-I.D to a cogeneration project activity operating only in electricity generation mode (submitted 25 Aug 08): SSC_224 (163 KB)
Clarification on the use of alternative biomass type than stated in the PDD applying AMS-I.D (submitted 31 Aug 08): SSC_227 (145 KB)
Applicability of AMS-I.D for project activity using biomass sourced from another country and using bunker fuel for the biomass transportation (submitted 13 Nov 08): SSC_246 (164 KB)
Clarification on vintage of data and survey period for assessment of biomass availability in AMS-I.D (submitted 17 Dec 08): SSC_255 (197 KB)
Applicability of AMS-I.D. and AMS-I.C. to a greenfield cogeneration project that is not implemented by a captive user (submitted 28 Dec 08): SSC_258 (245 KB)
Applicability of AMS-I.D for project activity involving an addition of back-pressure turbine generator in existing cogeneration system (submitted 11 Mar 09): SSC_286 (179 KB)
Change in the amount of CERs from registered PDD (submitted 05 Apr 09): SSC_299 (181 KB)
Is plant oil produced from sustainable plantations a renewable biomass, and is it eligible under AMS-I.D? (submitted 29 Apr 09): SSC_302 (169 KB)
Clarification on installed/rated capacity of hydropower project (submitted 02 Jun 09): SSC_314 (152 KB)
Request for revision on the monitoring of electricity in AMS-I.D (submitted 03 Jun 09): SSC_315 (182 KB)
Applicability of AMS-I.D to a small scale hydro-electric project activity with power density less than 10 W/sq.m (submitted 23 Jun 09): SSC_323 (151 KB)
Clarification on leakage in project activity using animal litter (submitted 13 Jul 09): SSC_328 (146 KB)
Clarification regarding project/leakage emissions from imported biomass (submitted 08 Sep 09): SSC_353 (213 KB)
Clarification on the applicability of AMS-I.D to a project activity utilizing waste heat from a process using renewable energy source (submitted 03 Feb 11): SSC_508 (213 KB)
Title Grid connected renewable electricity generation (333 KB)
Version number 12.0
Validity Valid from 10 Aug 07 to 13 Dec 07
Requests for registration can be submitted until 13 Aug 2008 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Clarification on the methodology applicable to the production of biodiesel to be used in heavy vehicles (submitted 29 Aug 07): SSC_122 (139 KB)
Clarification on the Applicability of Methodology AMS I.D. v10 (submitted 24 Oct 07): SSC_141 (152 KB)
Applicability conditions of AMS I.D, version 12 (submitted 03 Apr 08): SSC_176 (139 KB)
Title Grid connected renewable electricity generation (208 KB)
Version number 11.0
Validity Valid from 18 May 07 to 09 Aug 07
Requests for registration can be submitted until 09 Apr 2008 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Request for clarification on the applicability of AMS-I.D and on the definition of the baseline (submitted 15 May 07): SSC_101 (149 KB)
Title Grid connected renewable electricity generation (216 KB)
Version number 10.0
Validity Valid from 22 Dec 06 to 17 May 07
Requests for registration can be submitted until 17 Jan 2008 23:59:59 GMT
Sectoral scope(s) 1
Title Grid connected renewable electricity generation (215 KB)
Version number 9.0
Validity Valid from 27 Jul 06 to 21 Dec 06
Requests for registration can be submitted until 16 Feb 2007 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Further clarification on debundling definition as given in paragraph 62 of EB26 meeting report (submitted 20 Dec 06): SSC_076 (151 KB)
Addition of renewable energy capacity as per paragraph 4 of AMS I.D. (submitted 20 Dec 06): SSC_077 (141 KB)
Title Grid connected renewable electricity generation (1556 KB)
Version number 8.0
Validity Valid from 02 Mar 06 to 26 Jul 06
Requests for registration can be submitted until 21 Sep 2006 23:59:59 GMT
Sectoral scope(s) 1
Clarifications/Revisions* Request for clarification on revisions to AMS-I.D. “Grid Connected Renewable Electricity Generation" (submitted 04 May 06): SSC_050 (285 KB)
Kalasin Waste to Energy Project, AMS I.D. Weighted average grid CEF calculation (submitted 07 Sep 06): SSC_065 (179 KB)
Title Renewable electricity generation for a grid (43 KB)
Version number 7.0
Validity Valid from 27 Nov 05 to 01 Mar 06
Sectoral scope(s) 1
Clarifications/Revisions* Consideration of registered CDM projects in the build and operating margin (submitted 16 Dec 05): AM_CLA_0014 (28 KB)
Criteria for qualifying limits in retrofit/expansion projects in non dedicated power plants (submitted 01 Mar 06): SSC_043 (145 KB)
Title Renewable electricity generation for a grid (143 KB)
Version number 6.0
Validity Valid from 11 Oct 05 to 26 Nov 05
Sectoral scope(s) 1
Clarifications/Revisions* Bioenergy and the clean development mechanism (submitted 10 Mar 04): SSC_005 (57 KB)
Annex 2 - Avoidance of thermal energy input in small-scale industrial processes (submitted 23 Apr 05): SSC_014 (166 KB)
Clarifications on Type I-Renewable Energy and Type III-Other Project Activities (submitted 01 May 05): SSC_016 (145 KB)
Econergy Brasil-Fortuna (submitted 01 May 05): SSC_017 (166 KB)
Reducing non-rebewable wood energy that causes net carbon emissions from the land-use sector (submitted 07 Jun 05): SSC_018 (148 KB)
Recovery of Methane from Biomass Decay through Wastewater Treatment (submitted 09 Aug 05): SSC_024 (163 KB)
Proposal for a new small scale methodology for hydro electricity for a grid when the project consists of replacement of existing units (submitted 11 Aug 05): SSC_028 (202 KB)
Once calculated the emission factor for the baseline it is not clear if it will be necessary to updated it yearly (submitted 24 Oct 05): SSC_032 (36 KB)
Title Renewable electricity generation for a grid (154 KB)
Version number 5.0
Validity Valid from 24 Feb 05 to 10 Oct 05
Sectoral scope(s) 1
Clarifications/Revisions* Determination of relevant electricity grid boundaries in India – state grid vs. regional grid vs. national grid (submitted 27 Jul 05): AM_CLA_0001 (146 KB)
Title Renewable electricity generation for a grid (166 KB)
Version number 4.0
Validity Valid from 21 Oct 04 to 23 Feb 05
Sectoral scope(s) 1
Title Renewable electricity generation for a grid (521 KB)
Version number 3.0
Validity Valid from 29 Jun 04 to 20 Oct 04
Sectoral scope(s) 1
Title Renewable electricity generation for a grid (62 KB)
Version number 2.0
Validity Valid from 01 Dec 03 to 28 Jun 04
Sectoral scope(s) 1
Title Electricity generation for a system (147 KB)
Version number 1.0
Validity Valid from 31 Oct 02 to 30 Nov 03
Sectoral scope(s) 1
Clarifications/Revisions* Clarification on the penalty in case of instrument breakdown when calibration was overdue (submitted 23 Sep 13): SSC_696 (151 KB)

* Only the requests for clarification and revision that have been clarified by the SSC WG are displayed. To view all requests for clarification, go to this page. To view all requests for revision, go to this page.