AMS-II.D.: Energy efficiency and fuel switching measures for industrial facilities --- Version 13.0

Submit comments for improvement of this methodology (please login)

Title Energy efficiency and fuel switching measures for industrial facilities (1097 KB)
Word version (161 KB)

Tools referenced in this methodology:

Version number
13.0
Scale Small scale
Status Active
Validity Valid from 04 Oct 13 onwards
Sectoral scope(s) 3, 4
Clarifications/Revisions* Applicability of methodology AMS II.D version 13 to Automotive Coating Process (submitted 04 Dec 14): SSC_716 (155 KB)
The application of AMS-II.D for improving the blast efficiency of explosives used in mining operations (submitted 06 Feb 15): SSC_718 (136 KB)
Previous Versions
Title Energy efficiency and fuel switching measures for industrial facilities (219 KB)
Version number 12.0
Validity Valid from 18 Dec 09 to 03 Oct 13
Requests for registration can be submitted until 04 Jun 2014 23:59:59 GMT
Sectoral scope(s) 3, 4
Clarifications/Revisions* Applicability of AMS-II.D to total energy efficiency improvement by installing CHP at site (submitted 17 Jun 10): SSC_442 (231 KB)
Clarification on the applicability of AMS-II.D for project activities involving changes in raw material and production process in an automotive painting plant (submitted 16 Nov 10): SSC_489 (322 KB)
Clarification on the applicability of energy efficiency and fuel switching measures in commercial installations (submitted 26 Jun 11): SSC_546 (230 KB)
Applicability of AMS-II.D for "Integrated-Waste-Heat-Recovery-Fuel-Switch" Project (submitted 11 Nov 11): SSC_582 (221 KB)
Application of AMS-II.D in projects with a renewable energy generation component (submitted 24 Nov 11): SSC_587 (188 KB)
Clarification on the definition of a country specific technology in the FOIK guidelines (submitted 29 Feb 12): SSC_630 (156 KB)
Clarification on the applicability of AMS-III.Z/AMS-II.D to a project involving efficient brick production and displacement of non-renewable biomass (submitted 10 May 12): SSC_636 (162 KB)
Revision of AMS-II.D to clarify determining baseline procedure and production capacity for projects involving batch processes (submitted 24 May 12): SSC_642 (157 KB)
Clarification on applicability, project boundary, baseline calculation for project involving complex industrial process under AMS-II.D (submitted 06 Jul 12): SSC_643 (130 KB)
Title Energy efficiency and fuel switching measures for industrial facilities (241 KB)
Version number 11.0
Validity Valid from 02 Nov 07 to 17 Dec 09
Requests for registration can be submitted until 17 Aug 2010 23:59:59 GMT
Sectoral scope(s) 3, 4
Clarifications/Revisions* Energy efficiency measures through centralization of utility provisions in an industrial facility (submitted 04 Dec 07): SSC_148 (138 KB)
Applicability of AMS-II.D. to an energy efficiency project which installs modern kiln with a six-stage preheater instead of a five-stage preheater (baseline scenario) (submitted 16 Dec 07): SSC_150 (140 KB)
Clarification regarding two measures taken in the plant simultaneously – Fuel Switch and Energy efficiency (submitted 19 Feb 08): SSC_162 (191 KB)
Energy efficiency measures with more than one emission reduction component (submitted 03 Mar 08): SSC_166 (182 KB)
Clarification regarding the applicability of the small scale methodology AMS II.D. (submitted 09 Mar 08): SSC_169 (142 KB)
Applicability of AMS II.D for an energy efficiency project which installs modern kiln with a six-stage preheater instead of a five stage pre-heater (baseline scenario) (submitted 19 May 08): SSC_188 (139 KB)
Clarification request on applicability of AMS I.C and AMS II.D to a project activity at a Brickworks in Morocco (submitted 20 May 08): SSC_191 (139 KB)
Determination of the steam emission factor from a co-generation power plant (submitted 30 Jul 08): SSC_207 (138 KB)
Clarification on the use of the methodology AMS II.D for energy efficiency projects (submitted 01 Aug 08): SSC_213 (145 KB)
Applicability of the project activity composed of the energy efficiency measure with the reduction of carbonate compounds in the aid feed stock (submitted 10 Aug 08): SSC_222 (208 KB)
Revision of AMS-II.D to include energy-efficient project activities that involve changes in raw materials and/or production processes (submitted 04 Sep 08): SSC_228 (146 KB)
Revision for energy efficiency projects that reduce steam consumption (submitted 12 Oct 08): SSC_243 (175 KB)
Consideration of leakage due to transfer of equipment outside the project boundary in SSC methodologies (submitted 26 Jan 09): SSC_281 (167 KB)
Applicability of AMS-II.D for project activity using low energy intensive alternative raw material (submitted 30 Mar 09): SSC_295 (172 KB)
Use of internal benchmark IRR according to the Guidance on the assessment of investment analysis (submitted 18 May 09): SSC_319 (233 KB)
Applicability of AMS-II.D for project activity involving steam savings in an industrial process (submitted 05 Jul 09): SSC_326 (170 KB)
Inclusion of commercial facilities with district heating and cooling systems in the methodology (submitted 21 Jul 09): SSC_331 (183 KB)
Eligibility of improved recovery in the flotation process through the use of inert grinding media in the IsaMill (AMS-II.D) (submitted 06 Aug 09): SSC_341 (160 KB)
Revision of AMS-II.D to allow its applicability to project activities involving multiple industrial facilities (submitted 22 Sep 09): SSC_355 (210 KB)
Applicability of AMS-II.D for energy efficiency measures in gas manufacturing facility (submitted 21 Jan 10): SSC_382 (229 KB)
Applicability of AMS-II.D and III.B to a fuel switch and energy efficiency measures implemented at the same facility (submitted 24 Apr 10): SSC_421 (258 KB)
Title Energy efficiency and fuel switching measures for industrial facilities (272 KB)
Version number 10.0
Validity Valid from 10 Aug 07 to 01 Nov 07
Requests for registration can be submitted until 01 Jul 2008 23:59:59 GMT
Sectoral scope(s) 3, 4
Clarifications/Revisions* Proposed amendment to include technical line losses where electricity is the baseline (submitted 07 Aug 07): SSC_115 (140 KB)
Title Energy efficiency and fuel switching measures for industrial facilities (146 KB)
Version number 9.0
Validity Valid from 18 May 07 to 09 Aug 07
Requests for registration can be submitted until 09 Apr 2008 23:59:59 GMT
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (144 KB)
Version number 8.0
Validity Valid from 22 Dec 06 to 17 May 07
Requests for registration can be submitted until 17 Jan 2008 23:59:59 GMT
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (501 KB)
Version number 7.0
Validity Valid from 27 Nov 05 to 21 Dec 06
Requests for registration can be submitted until 16 Feb 2007 23:59:59 GMT
Sectoral scope(s) 3, 4
Clarifications/Revisions* Query on "same type of technology/measure" as per the "debundling" definition provided in the EB7 Meeting report, Annex 7 (submitted 23 Jul 06): SSC_062 (141 KB)
Revision of AMS II.D. to include Sectoral Scope 8:Mining and Mineral production (submitted 27 Nov 06): SSC_075 (154 KB)
Title Energy efficiency and fuel switching measures for industrial facilities (138 KB)
Version number 6.0
Validity Valid from 11 Oct 05 to 26 Nov 05
Sectoral scope(s) 3, 4
Clarifications/Revisions* Bioenergy and the clean development mechanism (submitted 10 Mar 04): SSC_005 (57 KB)
Reducing non-rebewable wood energy that causes net carbon emissions from the land-use sector (submitted 07 Jun 05): SSC_018 (148 KB)
SSC-PDD for CCP wastewater project (submitted 28 Jun 05): SSC_020 (139 KB)
Definition clarification of 15 GWh/yr threshold for thermal energy efficiency improvement projects (submitted 14 Aug 05): SSC_029 (149 KB)
Title Energy efficiency and fuel switching measures for industrial facilities (146 KB)
Version number 5.0
Validity Valid from 24 Feb 05 to 10 Oct 05
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (94 KB)
Version number 4.0
Validity Valid from 21 Oct 04 to 23 Feb 05
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (521 KB)
Version number 3.0
Validity Valid from 29 Jun 04 to 20 Oct 04
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (59 KB)
Version number 2.0
Validity Valid from 01 Dec 03 to 28 Jun 04
Sectoral scope(s) 3, 4
Title Energy efficiency and fuel switching measures for industrial facilities (147 KB)
Version number 1.0
Validity Valid from 31 Oct 02 to 30 Nov 03
Sectoral scope(s) 3, 4

* Only the requests for clarification and revision that have been clarified by the SSC WG are displayed. To view all requests for clarification, go to this page. To view all requests for revision, go to this page.