PoA monitoring report

Monitoring report data

Programme of Activities 00009251: PV Project Development in Chile
PoA period 28 Dec 2012 - 27 Dec 2019
Coordinating/Managing Entity C-Quest Capital LLC
Host Party(ies) Chile
Sectoral scopes 1 : Energy industries (renewable - / non-renewable sources)
Methodology Used ACM0002 ver. 12 - Consolidated baseline methodology for grid-connected electricity generation from renewable sources
Standardized baselines used N/A
Submitting DOE AENOR INTERNACIONAL, S.A.U.
Monitoring period start (YYYY/MM/DD) 2013/09/20
Monitoring period end (YYYY/MM/DD) 2016/10/31
Version of the PoA DD applicable to this monitoring report
Version of the monitoring report
Monitoring report PoA 9251 MR ver 1 221216.pdf (707 KB)
Monitoring report number 9251-MP1-MRP1
Please tick the checkbox if this monitoring report relates to a straddling monitoring period, i.e. one that begins in 2020 and ends in 2021. In such case, the monitoring results from 1 Jan 2021 will be processed as per the EB 108 temporary measures.

Please proceed to split the straddling monitoring period into two parts, whereby one is ending on 31 Dec 2020 and a second – beginning on 1 Jan 2021. Please upload the same monitoring report version to each of the two parts of the straddling monitoring period.

At issuance, the system will require you to upload two separate issuance requests for each of the two parts of the straddling monitoring period. You will have to upload the same version of certification/verification report to each of the "related" issuance requests.
No The DOE confirms that the first part of the straddling monitoring period ends on 31 Dec 2020 and that the second part - begins on 1 January 2021. The DOE shall create the first and the second part of the straddling monitoring period and upload the same monitoring report to each part back-to-back (so that both submissions are received by the secretariat at the same time).