NM0269: Cambodia Rural Electrification and Transmission Project (RETP) 220 kV Interconnection between Cambodia and Vietnam.

Initial submission

Reference NM0269
Title Cambodia Rural Electrification and Transmission Project (RETP) 220 kV Interconnection between Cambodia and Vietnam.
Submitted by DNV on 16 Apr 08
Documents
Current status 21 Oct 09 - Submission not approved
Historic statuses 16 Apr 08 - Submission received
22 Apr 08 - Successfully passed the Completeness Check
22 Apr 08 - Undergoing Assessment by the Secretariat
23 May 08 - Submission rated 1
28 May 08 - Undergoing desk reviews by experts
29 May 08 - Opened for public comments
18 Jun 08 - Closed for public comments
19 Aug 08 - Desk reviews completed by experts
08 Sep 08 - Awaiting Project Participant feedback on the preliminary recommendation
11 Sep 08 - Meth Panel recommendation issued
23 Oct 08 - Clarifications received from project participants

Call for public input

From 29 May 2008 (00:00:00 GMT) till 18 Jun 2008 (23:59:59 GMT).

Desk review(s)

Meth Panel recommendation and communication

Meth Panel 34
25 Aug 08

EB decision

C (141 KB)