09:45 27 Dec 24
Info Report Check
Submission incomplete:
1: The PP/DOE are requested to complete all the PDD sections for the description of the project activity as per EB 48 Annex 60 paragraph 10 (a).
As per Table A.4.3 given on page 7 of the PDD, an enclosed flare will be installed however, page 14 of validation report (VR) states that open flare will be installed. PDD and VR so not provide consistent information.
2: The PP/DOE are requested to explain the methodological choices for the calculation of the baseline, project emissions and emission reductions as per EB 48 Annex 60 paragraph 10 (a).
PDD on page 29 states that, in accordance with AMS-III.H./Version 16 paragraph 26, historical records of 1 year have been used to determine the baseline system’s COD removal efficiency. However, as per page 23 of the validation report 10-day measurement campaign was carried out to determine COD removal efficiency of baseline wastewater treatment system. PDD and validation report do not provide consistent information. PDD does not provide data measured for inlet and outlet COD that is used to calculate the COD removal efficiency of baseline system.
1: The PP/DOE are requested to complete all the PDD sections for the description of the project activity as per EB 48 Annex 60 paragraph 10 (a).
As per Table A.4.3 given on page 7 of the PDD, an enclosed flare will be installed however, page 14 of validation report (VR) states that open flare will be installed. PDD and VR so not provide consistent information.
2: The PP/DOE are requested to explain the methodological choices for the calculation of the baseline, project emissions and emission reductions as per EB 48 Annex 60 paragraph 10 (a).
PDD on page 29 states that, in accordance with AMS-III.H./Version 16 paragraph 26, historical records of 1 year have been used to determine the baseline system’s COD removal efficiency. However, as per page 23 of the validation report 10-day measurement campaign was carried out to determine COD removal efficiency of baseline wastewater treatment system. PDD and validation report do not provide consistent information. PDD does not provide data measured for inlet and outlet COD that is used to calculate the COD removal efficiency of baseline system.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: