Submission incomplete:
1: As per the PDD, the value of parameter "ConvFactor" is sourced from version 02 of ACM0001, which is no longer valid. Please refer to VVS-PA, paragraph 112 (a).
2: The DOE is requested to explain how the local stakeholder consultation (LSC) has been carried out as per paragraph 107 of the PS-PA considering that LSC took place on 29 May 2019 while the project start date was 7 September 2018. In doing so, the DOE is also requested to determine whether there are applicable host Party rules on local stakeholder consultation. Refer to paragraphs 130-132 of VVS-PA.
1: As per the PDD, the value of parameter "ConvFactor" is sourced from version 02 of ACM0001, which is no longer valid. Please refer to VVS-PA, paragraph 112 (a).
2: The DOE is requested to explain how the local stakeholder consultation (LSC) has been carried out as per paragraph 107 of the PS-PA considering that LSC took place on 29 May 2019 while the project start date was 7 September 2018. In doing so, the DOE is also requested to determine whether there are applicable host Party rules on local stakeholder consultation. Refer to paragraphs 130-132 of VVS-PA.
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: