Submission incomplete:
1: The PP/DOE are requested to present the sensitivity analysis of the investment analysis as per EB 48 Annex 60 paragraph 10 (a).
The sensitivity analysis for the investment costs parameter is not in the associated investment analysis spreadsheet. The PP/DOE are requested to include the relevant calculations in the spreadsheet.

2: The DOE is requested to state that the estimates in the PDD are reasonable for data and parameters that are monitored during implementation and are available after validation as per VVM v1.2 paragraph 91.
In Section B7.1 of the PDD, the exported electricity is 35,083.8 kWh, imported electricity is 0 kWh and net electricity is 36,082.4 MWh. However, this is not consistent with the net amount of electricity mentioned in other sections of the PDD and the CER calculation spreadsheet, in terms of the amounts and in the units.

3: The DOE is requested to address the changes made to the project deign since the global stakeholder consultation was conducted as per VVM v1.2 paragraph 173(c).
The VR has not addressed the changes made to project design since the global stakeholder consultation.