Submission incomplete:
1: The DOE is requested to provide information on the steps taken to validate the project starting date as per VVM v 1.2 paragraph 104 (a).
The DOE shall further explain how it has validated the project starting date given that there appears to be some earlier real actions before 26/01/2004(EPC contract), e.g. the supply contract “Oferta Vatech Equipos”(18/03/2002), the agreement with Owbow Power Co. (December 2002, page 118 of validation report), engineering contract HDG_GBEL (2001).
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
(i). The DOE shall further explain the availability and validity of each input value (both for the investment analysis and benchmark determination) at the time of investment decision.
(ii). Please provide the information on the time when the source of input value "annual power generation" (EGHP Hydrology study calculation spreadsheet “Generation EGHP”) was available.
(iii). The DOE shall further substantiate the suitability of total investment given that only the 70% of the total project investment costs.
1: The DOE is requested to provide information on the steps taken to validate the project starting date as per VVM v 1.2 paragraph 104 (a).
The DOE shall further explain how it has validated the project starting date given that there appears to be some earlier real actions before 26/01/2004(EPC contract), e.g. the supply contract “Oferta Vatech Equipos”(18/03/2002), the agreement with Owbow Power Co. (December 2002, page 118 of validation report), engineering contract HDG_GBEL (2001).
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
(i). The DOE shall further explain the availability and validity of each input value (both for the investment analysis and benchmark determination) at the time of investment decision.
(ii). Please provide the information on the time when the source of input value "annual power generation" (EGHP Hydrology study calculation spreadsheet “Generation EGHP”) was available.
(iii). The DOE shall further substantiate the suitability of total investment given that only the 70% of the total project investment costs.