Info Report Check
Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In doing so please provide: i) the breakdown on the investment cost and its validation, ii) the details (list, location, capacity etc) of the geothermal project activities used to crosscheck the O&M costs, iii) validation on overhead costs, cost for make-up wells, cost for major-work over and overhaul cost, and iv) report on how it validated the auxiliary power consumption (4%) and losses (2%) .

2: The DOE is requested to provide information on how it has validated the suitability of the benchmark as per VVM v 1.2 paragraph 114 (b) and EB62 Annex 5 Guidance 15.
In doing so, the PP/DOE report and validate the parameters used to calculate the WACC benchmark.