Submission incomplete:
The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
1. The DOE is requested to clarify why MERC (Maharashtra Electricity Regulatory Commission) tariff order dated 24/11/2003 has been used to validate input parameters such as O&M cost, D/E ratio and deration rate considering that the project activity is located in Tamilnadu state which has a specific tariff order issued by TNEB.
2. The DOE is requested to provide a breakdown of the actual project cost of all wind turbines validated from the purchase orders dated 08/01/2005 and other mandatory costs as mentioned in the validation report.
3. The DOE is requested to report the date of loan sanction letter issued by the bank.
The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
1. The DOE is requested to clarify why MERC (Maharashtra Electricity Regulatory Commission) tariff order dated 24/11/2003 has been used to validate input parameters such as O&M cost, D/E ratio and deration rate considering that the project activity is located in Tamilnadu state which has a specific tariff order issued by TNEB.
2. The DOE is requested to provide a breakdown of the actual project cost of all wind turbines validated from the purchase orders dated 08/01/2005 and other mandatory costs as mentioned in the validation report.