1: The DOE is requested to describe the steps undertaken to assess if the monitoring arrangements are feasible to be implemented within the project design as per VVM v1.2 paragraph 124(b).
The DOE is requested to describe how it assessed the feasibility of the arrangements to monitor the electricity imported through the back up line.

2: The DOE is requested to report if it has applied standard auditing techniques for follow-up actions as per VVM v1.2, paragraphs 33 (b) and 62.
In particular, the DOE is requested to appropriately justify that the site visit was not required and that no further issues could be assessed through onsite visit.