Info Report Check
Submission incomplete:
1: The documents submitted are not internally and mutually consistent. EB 48 Annex 60 paragraph 7 (b).
The values for the Total Cost are not consistent between the submitted spreadsheets: 205,336 (10,000 Yuan) in the Enclosure 1, and 202,996 (10,000 Yuan) in the Enclosure 2.

2: The PP/DOE are requested to describe in detail the monitoring plan as per EB 48 Annex 60 paragraph 10 (a).
The PDD states that the power grid company shall allocate the data monitored by M1 and M2 through certain calculation method in order to determine the on-grid electricity quantity of both Baopinghe and Sandaowan hydropower stations. The calculation method is subject to that specified in the power purchase agreement and other relevant documents signed between the project owner and provincial power grid.

The PDD does not describe the calculation method for EGy.