Submission incomplete:
The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In doing so, DOE shall further substantiate the suitability of the total investment cost by cross-checking against available data considering that during the on-site visit, the DOE found that most of the project sites were already installed.
The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In doing so, DOE shall further substantiate the suitability of the total investment cost by cross-checking against available data considering that during the on-site visit, the DOE found that most of the project sites were already installed.