07:18 26 Nov 26
Info Report Check
Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
i) According to the PDD p20, the IRRs using project costs in offer letters are different from IRRs using project costs in purchase order.
The DOE is requested to further clarify this issue since the VR does not report these differences and the resulting IRRs for some projects are very close the benchmarks. The DOE is therefore required to explain how it has validated the appropriateness of project costs considering that the offer letters and purchase orders are both sourced from the technology provider and that the period between each of these evidences is just one or a few months.
The same situation occurs with generation according to Tariff Orders.
ii) Several typos and differences were found in dates and names of companies as shown below:
-The VR p 17 states that the board resolution for "Basavaraj N Patil" and "Frontline Corporation Ltd" occurred on 06th November 2007 and 31st August 2008 respectively but the VR p 23 and 24 states that those boards resolution were on 06th November 2010 and 31st January 2008.
-The VR p 17 states that the offer letter for "Basant Agro Tech (India) Ltd" and "Kundanmal Mukanmal Traders Pvt. Ltd" were from 29th August 2007 and 18th March 2008 respectively but the VR p 24 states that the dates were 29th August 2009 and 15th March 2007.
-The VR p 17 states that the offer letters for "Frontline Corporation Ltd" were from Pioneer Wincon dated 4th January 2008 and Shriram EPC dated 18th January 2008.
The VR p 24 states that the letters were from Shriam Leitwind Limite and RRB Energy Ltd dated 15th March 2007.
- The VR p 23 reports that MAT:11.22% and IT:33.66% for equity projects
The VR p 26 and 27 reports that MAT:11.33% and IT:33.99% for the other projects. However, some of the web page links used as reference are the same and some figures are not explicitly shown when accesing the links.
-The VR contains a typo in page 25 where it is reported that: Equity 70% - Debt 30%, and explains the sources as "the bank loan sanction letters of the respective companies in support of the 70:30% (debt: equity)".
Clarification and corrected information is required
2: The DOE is requested to include information on how it has validated sensitivity analysis of the investment analysis as per VVM v1.2 paragraph 111 (e).
The DOE only reported the result of the +/-10% variations as indicated in the PDD without assessing the variations required to reach the benchmarks and the likelihood of these conditions.
Some of the projects result in IRR very close to the benchmark when using the project cost from the purchase order instead of the cost from the offer letter. The DOE is requested to assess and clarify these differences considering that the offer letters and purchase orders are both sourced from the technology provider and that the period between each of these evidences is just one or a few months.
Clarification is required
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
i) According to the PDD p20, the IRRs using project costs in offer letters are different from IRRs using project costs in purchase order.
The DOE is requested to further clarify this issue since the VR does not report these differences and the resulting IRRs for some projects are very close the benchmarks. The DOE is therefore required to explain how it has validated the appropriateness of project costs considering that the offer letters and purchase orders are both sourced from the technology provider and that the period between each of these evidences is just one or a few months.
The same situation occurs with generation according to Tariff Orders.
ii) Several typos and differences were found in dates and names of companies as shown below:
-The VR p 17 states that the board resolution for "Basavaraj N Patil" and "Frontline Corporation Ltd" occurred on 06th November 2007 and 31st August 2008 respectively but the VR p 23 and 24 states that those boards resolution were on 06th November 2010 and 31st January 2008.
-The VR p 17 states that the offer letter for "Basant Agro Tech (India) Ltd" and "Kundanmal Mukanmal Traders Pvt. Ltd" were from 29th August 2007 and 18th March 2008 respectively but the VR p 24 states that the dates were 29th August 2009 and 15th March 2007.
-The VR p 17 states that the offer letters for "Frontline Corporation Ltd" were from Pioneer Wincon dated 4th January 2008 and Shriram EPC dated 18th January 2008.
The VR p 24 states that the letters were from Shriam Leitwind Limite and RRB Energy Ltd dated 15th March 2007.
- The VR p 23 reports that MAT:11.22% and IT:33.66% for equity projects
The VR p 26 and 27 reports that MAT:11.33% and IT:33.99% for the other projects. However, some of the web page links used as reference are the same and some figures are not explicitly shown when accesing the links.
-The VR contains a typo in page 25 where it is reported that: Equity 70% - Debt 30%, and explains the sources as "the bank loan sanction letters of the respective companies in support of the 70:30% (debt: equity)".
Clarification and corrected information is required
2: The DOE is requested to include information on how it has validated sensitivity analysis of the investment analysis as per VVM v1.2 paragraph 111 (e).
The DOE only reported the result of the +/-10% variations as indicated in the PDD without assessing the variations required to reach the benchmarks and the likelihood of these conditions.
Some of the projects result in IRR very close to the benchmark when using the project cost from the purchase order instead of the cost from the offer letter. The DOE is requested to assess and clarify these differences considering that the offer letters and purchase orders are both sourced from the technology provider and that the period between each of these evidences is just one or a few months.
Clarification is required