Submission incomplete:
The PP/DOE are requested to list all the data and parameters to be monitored in line with applied methodology as per EB 48 Annex 60 paragraph 10 (a).
The PP/DOE is requested to provide missing information on and include all the monitored parameters, introduced in the apportioning procedures to calculate the net electricity supplied to the grid, in the section B.7.1. of the PDD given that the quantity of net electricity generation supplied by the project plant to the grid in year y should be based on continuous measurement and at least monthly recording.