Info Report Check
Submission incomplete:
1: The PP/DOE are requested to list all relevant assumptions, data, input values and references used in the investment analysis as per EB 48 Annex 60 paragraph 10 (a).
The PDD does not list the references of the input values used in the investment analysis.
2: The PP/DOE are requested to include the details of each parameter listed as per EB 48 Annex 60 paragraph 10 (a).
The PDD does not include the details (reference) of the 80% digester removal efficiency and POME reduction rate values used in the emission reductions calculations.
3: The DOE is requested to state whether the data and parameters are conservative and appropriate if they are fixed ex-ante (not need to monitor) during the project activity crediting period as per VVM v1.2 paragraph 91.
There is no information on the suitability of using a 80% digester removal efficiency in the emission reductions calculations.
4: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
There is no information in the Validation Report if the following input values used in the investment analysis were applicable at the time of the investment decision: project cost, O&Mcost and sale price of palm kernel shell. Further, the Validation Report does not describe the results of the cross-checks made with the project reference number 1783.
5: The DOE is requested to provide information on how it has assessed the credibility of the barrier analysis as per VVM v 1.2 paragraph 118.
The DOE should provide information on how it has assessed the credibility of the barrier due to prevailing practice presented in the PDD.
1: The PP/DOE are requested to list all relevant assumptions, data, input values and references used in the investment analysis as per EB 48 Annex 60 paragraph 10 (a).
The PDD does not list the references of the input values used in the investment analysis.
2: The PP/DOE are requested to include the details of each parameter listed as per EB 48 Annex 60 paragraph 10 (a).
The PDD does not include the details (reference) of the 80% digester removal efficiency and POME reduction rate values used in the emission reductions calculations.
3: The DOE is requested to state whether the data and parameters are conservative and appropriate if they are fixed ex-ante (not need to monitor) during the project activity crediting period as per VVM v1.2 paragraph 91.
There is no information on the suitability of using a 80% digester removal efficiency in the emission reductions calculations.
4: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
There is no information in the Validation Report if the following input values used in the investment analysis were applicable at the time of the investment decision: project cost, O&Mcost and sale price of palm kernel shell. Further, the Validation Report does not describe the results of the cross-checks made with the project reference number 1783.
5: The DOE is requested to provide information on how it has assessed the credibility of the barrier analysis as per VVM v 1.2 paragraph 118.
The DOE should provide information on how it has assessed the credibility of the barrier due to prevailing practice presented in the PDD.