Submission incomplete:
1: The PP/DOE are requested to describe in detail the monitoring plan as per EB 48 Annex 60 paragraph 10 (a).
The PP is requested to provide further information regarding the sampling plan for monitoring the parameters; Annual average distance driven by project vehicles in year y (DDi) and Specific electricity consumption per km per project vehicle category i in year y (SEC PJ,km,i), in particular;
1) estimation of sample size of 100 (DDi) and 50 (SEC PJ,km,i)
2) how randomness in the selection of sample vehicle will be ensured
3) whether the same set of sample vehicles will be used to collect monitoring data for both the parameters

2: The DOE is requested to state whether the data and parameters are conservative and appropriate if they are fixed ex-ante (not need to monitor) during the project activity crediting period as per VVM v1.2 paragraph 91.
The DOE is requested to clarify how it validated the appropriateness of the ex-ante value for specific fuel consumption gasoline scooters (2.37 l/100km) obtained via a survey carried out by the PP and how the requirements under the General Guidelines for Sampling and Surveys for Small-Scale CDM Project Activities were met.

3: The DOE is requested to describe the steps undertaken to assess if the monitoring arrangements are feasible to be implemented within the project design as per VVM v1.2 paragraph 124(b).
The DOE is requested to validate the sample size estimation for the following parameters in the PDD;
1) 100 electric vehicles of each category for monitoring annual average distance driven by project vehicles in year y
2) 50 electric vehicles of each category for monitoring specific electricity consumption per km per project vehicle category i in year y
3) sampling approach applied by the PP for selection of samples and whether data for multiple parameters will be obtained from the sample/different sample set(s).