Info Report Check
Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
(i) The DOE shall explain why the assumed annual operation hour of the project activity (7200 hours) is lower than the average operation hour of the 3rd clinker production line (7920 hours);
(ii) The DOE shall explain how it has validated the suitability of the assumed lifetime of the project activity (15 years) as per VVM version 1.2, paragraph 111 (b);
(iii) The DOE shall explain why the power generation in the 1st year only accounts for 90% of the power generation in normal years; and
(iv) The DOE shall explain how it has validated the validity of the interest rate at the time of the investment decision given that the investment decision (dated 7/12/2009) was made one year after the completion of FSR (dated 10/2008).

2: The DOE is requested to provide information on how it has assessed the existence of the similar projects for common practice analysis as per VVM v 1.2 paragraph 121 (b).
The DOE shall explain how it has validated that all the plants that deliver the same output or capacity in the applicable geographical area have been included as per step 2, given that only the UNFCCC website was used as the data base to identify "All the plants that deliver the same output or capacity".