Info Report Check
Submission incomplete:
1: The DOE is requested to provide information on the steps taken to validate the project starting date as per VVM v 1.2 paragraph 104 (a).
In doing so, please explain how the DOE validated the contract with turbine supplier to be the earliest commitment made by the project participant out of all the activities related to both power plants. in doing so, please provide clear timelines of the project and CDM implementation for each hydro power plant.

2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In doing so, the DOE shall provide: a) separate investment analysis for each hdro power plant; and b) detailed validation of all relevant input values used in the calculation of the IRR, which includes validation of: i) the total investment: breakdown of the cost, clearly distinguishing the cost related to the modification of the old plant and the construction of the new plant; ii) the O&M costs: the breakdown of the costs; iii) the net electricity export: the estimation of the operating hours and any discounting factor applied such as the line loss; iv) the electricity tariff.

3: The DOE is requested to provide information on how it has assessed each barrier presented as per VVM v 1.2 paragraph 118 (a) and (b).
In doing so, the DOE shall provide: a) a clear definition of "small-hydro projects" in terms of the installed capacity; b) list of projects considered; and c) how it is interpreted as a barrier, in the context of the prevailing practice barrier.