Info Report Check
Submission incomplete:
1: The PP/DOE are requested to list all the data and parameters to be monitored in line with the applied methodology as per EB 48 Annex 60 paragraph 10 (a).
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
Explain how the "plant load factor" value was valid and applicable at the time of the investment decision (Investment Guidelines v.5 paragraph 6).
Explain how the "Interest rate on loan" value was valid and applicable at the time of the investment decision (Investment Guidelines v.5 paragraph 6).
The crosscheck of the input value "Operation and Maintenance cost" and its escalation is incomplete.
Please note the inconsistent references to the Offer Letter (21 Jul 2009) /10/ and the Power Purchase Agreement (30 Aug 2010) /2/.
1: The PP/DOE are requested to list all the data and parameters to be monitored in line with the applied methodology as per EB 48 Annex 60 paragraph 10 (a).
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
Explain how the "plant load factor" value was valid and applicable at the time of the investment decision (Investment Guidelines v.5 paragraph 6).
Explain how the "Interest rate on loan" value was valid and applicable at the time of the investment decision (Investment Guidelines v.5 paragraph 6).
The crosscheck of the input value "Operation and Maintenance cost" and its escalation is incomplete.
Please note the inconsistent references to the Offer Letter (21 Jul 2009) /10/ and the Power Purchase Agreement (30 Aug 2010) /2/.