Submission incomplete:
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In particular, the DOE should provide a validation opinion on how it has cross-checked the suitability of the Book Depreciation Rate, the Accelerated Depreciation, the Working Capital and the Loan Interest Rate. Moreover, the DOE should confirm that the MAT has been appropriately applied.
2: The DOE is requested to provide information on how it has assessed the existence of the similar projects for common practice analysis as per VVM v 1.2 paragraph 121 (b).
In doing so, the DOE should further explain why similar activities with installed capacity of less that 15MW were excluded from the analysis.
1: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
In particular, the DOE should provide a validation opinion on how it has cross-checked the suitability of the Book Depreciation Rate, the Accelerated Depreciation, the Working Capital and the Loan Interest Rate. Moreover, the DOE should confirm that the MAT has been appropriately applied.
2: The DOE is requested to provide information on how it has assessed the existence of the similar projects for common practice analysis as per VVM v 1.2 paragraph 121 (b).
In doing so, the DOE should further explain why similar activities with installed capacity of less that 15MW were excluded from the analysis.