Submission incomplete:
1: The DOE is requested to confirm the accuracy of the financial calculations carried out for the investment analysis as per VVM v 1.2 paragraph 114 (c).
In doing so , please provide information on the residual value.
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
The DOE has not reported how it has validated that IRR calculation with with an installed capacity of 16 MW is more conservative than it is with 12MW.
1: The DOE is requested to confirm the accuracy of the financial calculations carried out for the investment analysis as per VVM v 1.2 paragraph 114 (c).
In doing so , please provide information on the residual value.
2: The DOE is requested to include information on how it has validated the input values to the financial calculations as per VVM v 1.2 paragraph 114 (a).
The DOE has not reported how it has validated that IRR calculation with with an installed capacity of 16 MW is more conservative than it is with 12MW.